Figure shoreline and slope tonnage from the armor layer depth, not from a shallow landscape-rock spread.

Enter your project dimensions

ft
Enter a length greater than 0
ft
Enter a width greater than 0
ft
Enter a diameter greater than 0
in
Enter a depth between 0.25 and 24 inches

A ton of riprap covers roughly 17 square feet. That figure is correct. Because armor stone is installed in layers 12 inches thick or more, each ton covers only a small share of the area covered by landscape rock. This calculator bases the estimate on layer thickness and 3,100 lb per cubic yard for riprap generally ranging from 4 to 12 inches and larger.

How to measure an armored bank

  1. Take the slope measurement along the face of the bank, rather than across level ground, then multiply it by the shoreline or channel length.
  2. Use a layer depth of 1.5 to 2 times the largest stone dimension. For erosion control, 12 inches is the minimum working depth.
  3. To find cubic yards, divide cubic feet by 27; then multiply by 1.55 for tons.
Tons = (Slope-face area sq ft × Layer thickness in ÷ 12) ÷ 27 × 1.55

Tons and coverage

Layer thickness1 ton coversTons per 100 sq ft
12 inches≈ 17 sq ft5.7
18 inches≈ 12 sq ft8.6
24 inches≈ 9 sq ft11.5

Stone placement basics

  • Place fabric or bedding beneath the rock: use non-woven geotextile, or 3-4 inches of #4 stone. Riprap laid directly on soil can appear stable for a season before erosion below the bank causes it to settle.
  • Build the toe into the bank. Set the lowest stones below the waterline or anticipated scour depth, since failure works upward from the bottom.
  • Before placing stone, shape the slope to 2:1 or flatter. A steeper bank calls for engineering rather than more rock.
  • Use a machine or hand placement for the exposed top course, fitting stones together so they interlock instead of stopping where they land.
  • Extend the apron 4-6 pipe diameters downstream from culvert outlets. That is the area where flowing water cuts into the ground.

Example: 50 feet of pond bank

Start with the shoreline area: 50 feet of bank at a 6-foot slope face equals 300 square feet. For an 18-inch-thick layer, 300 x 1.5 = 450 cubic feet = 16.7 cubic yards, or roughly 26 tons of riprap. Plan for 27 to cover the small allowance. Use a roll of geotextile beneath it, or choose about 4 tons of #4 stone for a rock bed. Before you order, check the truck path. The final 20 feet near a pond can be soft, and relocating placed stone twice means paying for placement twice.

Following the first major storm

After the water level recedes, walk the bank and inspect the toe for moved rock, exposed soil between the stones, or visible fabric. Put shifted stones back in place, use reserve stone to fill sparse areas, and inspect the outfall apron for erosion. A quick inspection a couple of times each year, especially after spring melt, keeps the riprap in order with little upkeep.

Stone sizes at a glance

Select riprap for the water conditions. Four to eight inch stone works at pond banks, downspout outfalls and slow streams. Use eight to twelve for lake shorelines facing boat wake and for faster channels. Highway and spillway work has its own engineered stone classes and layer depths, so follow the project drawing instead of this page. If two sizes seem possible, use the larger stone with a thicker layer; added weight allows more margin.

Riprap amounts, sizes and installation

How can I estimate the rip rap I need?
Multiply slope-face area by layer thickness in feet, divide the result by 27, and multiply by 1.55. A 10 x 10 test patch with a 12 inches layer equals 37 cubic feet, or about 2.1 tons.
What coverage comes from 1 ton of riprap?
At a 12-inch layer, allow about 17 square feet per ton; at 18 inches, allow 12. For budgeting at the standard layer, use 5.5 to 6 tons for every 100 square feet.
What does a 1 ton pile of rip rap look like?
A ton makes a pile of about two-thirds of a cubic yard, close to a washing machine in volume. At the 6-8 inch size, that is about 25-35 stones. It can look modest in a pile, then covers only a 4 x 4 bank section once spread to the proper depth.
What is the cost for 1 ton of rip rap?
RipRap costs more than construction stone and is priced by size class; see the current figure on our RipRap product page, with delivery free. Fabric and bedding stone add a fraction more, and they are an important part of the system to install correctly.
What depth should a rip rap layer have?
Use a layer no thinner than 12 inches. Size the depth from one and a half times the largest stone up to two times that dimension. Residential 4-12 inch stone commonly needs 12-18 inches, while larger rock or moving water calls for 24.
Is hand placement possible for rip rap?
Hand placement works for stone up to about 6-8 inch, with gloves and a strong back: one ton means 25-35 lifts. Larger pieces call for a machine. A skid steer can set stone in an hour that a crew would hand-place in a day.

Plan the bank protection.

Get RipRap by the ton with free delivery, along with #4 bedding stone for beneath it.

Shop RipRap

Order materials to fit your project result